Tuesday, 28 April 2015

Time Schedule

Tuesday 28/04/15 - Time Schedule
TIMETASK
13:20Arthur getting changed
13:30Arthur getting changed
13:40Arrive at the Media Room and start moving to location
13:50Set up (Audio gear & levels, Lighting, Camera shot WB & Iris)
14:00Finish setup & start Filming
14:10Film: Initial Over the shoulders
14:20Film: Initial Over the shoulders
14:30Film: Close-ups
14:40Film: Close-ups
14:50Film: Tracking Shots
15:00Film: Additional shots (wide & low angle front facing mid shot)
15:10Film: Additional shots (wide & low angle front facing mid shot)
15:20Start packing up
15:30Finish Packup and go back to class

Location

Location Scouting
 
1 of the 2 locations we decided to choose for our shoot was outdoors in a carpark underneath a school building.  
  
 

Monday, 27 April 2015

Test Shoot

Our group went on a test shoot to feel for the location and experiment with more difficult shots. This footage was from of one of our more complicated shots. As seen the shot is very shaky, so we brainstormed as to how to reduce the movement in the shot, such as using a car or some kind of wheeled device. We also learnt that we needed to pay close attention to the end of the carpark as it comes out of the shadows and is overexposed. We also experimented with different shot sizes with the talent in the foreground such as a mid close up with the talent on the third.